November 2012 Final Status Report

Status: All Goals Accomplished


November 2012 Goals:
14 Bug Fixes - 19 have been done
Continued Doctrine Conversion - In progress
Test the New Message System on all islands - In progress
Continued Facebook updates - In progress

Items Completed but Not Planned:
New Welcome Email - This was a community group effort, thank you very much! - Email is now live

Colors on the burn down chart have been swapped

November Burn down Chart (Bug Fixes)

(http://i49.tinypic.com/2dqosg4.png)